For point 3, in MD04 you can see there is a requirement in column 3. When I run MD01 with NETCH, planned orders go in column 3 and reqs go in column 7, however, my batch job which uses NEUPL puts both planned orders and reqs in column 3. You have to click on the line to see if it is a requisition or a planned order.