Re: Refresh of ATP Server ?

$
0
0

Hello guys,

 

 

Thanks a lot for your input.

 

I have thought for a moment that the issue is solved, but it still persists.

We have deactivated the ATP Server for now because it was affecting our productive system. Now the ATP Check runs very slow.

 

I have scheduled background jobs after each MRP RUN (2 times per day).

The ATP results are still not reliable.

During the day, the planners are running MRP manually and it does not update the ATP Buffer.

 

Do you recommend a custom job which can be triggered automatically after each MRP Run (manual or in background) ?

 

 

Many thanks,

Alex