Hi :
QUESTION 1:
In OP4A - Define Shift Sequence via Grouping (Work Break Sch., Shift definition & Shift Sequence).
I understood how the functionality works for 7 days @ 3 Shifts.
But how this is transformed to a Months (30 Days).
QUESTION 2:
What is the purpose of "DEFINE PERIOD PATTERN KEY" via OP11. Where we use this key.
QUESTION 3:
In OP4A we already defined grouping which contains shift start/end time and we assign the same in OP36 - Default Capacity. Then why we need to specify the start/end/break length again in OP36 under Standard available capacity.
Thanks in Advance,
Dinesh Kumar V.