Re: Issue in Start / Finish Timings of operations in Planned Order in Item with two operations @ two different work Centers

$
0
0

Hello,

 

Since you have only two operation then in this case you can define your branching and returning operation as same.

 

Go to CA02> Sequence> new entries> Parallel sequence> give branching and returning operation and maintain the operations in it.

 

Then you can maintain the both operation in parallel routing and the same will be copied to your production order and need to confirm while doing the confirmation.

 

Regards,

Anupam Sharma